Foundation
- It is made according to foundation projects and geotechnical studies:
- in the ground (120 cm):
- concrete equalizer in ditches digged for housed bearings;
- armed housed bearings;
- crossbeam connection between bearings and all intersections. .
- Above ground (100 - 120 cm):
- continue armed beams to share finite;
- isolate perimetral all the spaces between the concrete beams, inside them;
- fill with soil and compacting;
- fill with washed stone, approximately 20 cm and compacting;
- isolate the entire area with expanded polystyrene by 5cm;
- place the polyethylene foil;
- install reinforcement for the board;
- pour the board.
Note: The concrete used is ordered in concrete station, the quality of the draft resistance and is cast with the vibration pump.